Inspect before signing.
Document damage or shortages on the Bill of Lading and notify P3 immediately. Stage pieces level on wood blocks—never directly on the ground.
CONTRACTORS / FIELD WORKFLOW
Polymer concrete changes the material—not the familiar precast sequence. Start with the plans you have, then move from delivery through installation with the relevant P3 and component-manufacturer guidance close at hand.
01 / BEFORE THE BID
These are the main factors we use to quote every structure. If you have this information ready to go, it helps us turn pricing around quickly. If you don’t have it all, just send whatever plans and specifications you have. P3 can perform the structure takeoff, review the product requirements, and come back with any questions needed to complete your quote.
Send plans + request pricing02 / DELIVERY + LIFTING
Confirm component weights and use the embedded side lift pins with a spreader bar, standard chains and hooks. Keep chains within 30° of vertical and clear of the component.
Document damage or shortages on the Bill of Lading and notify P3 immediately. Stage pieces level on wood blocks—never directly on the ground.
Verify the component weight and rated rigging. Lift only from the embedded side pins; do not use pipe openings or joint faces.
Keep chains off the structure, avoid impact and confirm that joining surfaces, connectors and lifting points are clean and undamaged.
03 / INSTALLATION
Set on a firm, stable foundation. Replace unstable material with compacted crushed stone and provide the bedding required for the design loads.
DO NOT CONTINUE IFThe subgrade is soft, pumping, unstable or different from the approved condition.Remove dirt, grease and contaminants. Install the project-specified butyl, gasket or polymer grout in the bell or keyway exactly as its manufacturer directs.
DO NOT CONTINUE IFA joint face is chipped, contaminated, misaligned or will not seat evenly.Install the selected flexible rubber connector in accordance with ASTM C923 and its manufacturer instructions. Corrugated pipe requires the specified adapter.
DO NOT CONTINUE IFThe actual O.D., opening, connector model or approved shop drawing do not agree.Use project-specified material, hand-place and tamp in 12–24 inch lifts, and keep heavy equipment off the manhole during backfill.
DO NOT CONTINUE IFBackfill is moving the stack, opening joints or loading a pipe connection.04 / FIELD DOCUMENTS
These are reference documents, not a substitute for the approved project submittal. Confirm the model, size, material, and revision supplied for your structure before installation.
The controlling field sequence for inspection, unloading, rigging, foundation, assembly, connections and backfill.
OPEN PDF 02LIFTINGEmbedded lift-pin composition and 4,000 lb working-load reference. Rigging capacity still follows the marked component weight and lift plan.
OPEN PDF 03JOINT GASKETPre-lubricated gasket selection, identification, pressure rating and five-step installation guidance.
OPEN PDF 04BUTYL SEALANTManufacturer product data for the project-specified butyl joint-sealing system.
OPEN PDF 05PIPE CONNECTORASTM C923 connector selection by actual pipe O.D., required hole size and manufacturer torque guidance.
OPEN PDF 06LARGE PIPE CONNECTORASTM C923 connector ranges for 18–51 inch pipe, with required opening and minimum structure size.
OPEN PDF 07EXTERIOR JOINT WRAPASTM C877 Type III, Type A exterior joint-wrap properties and surface preparation, application and overlap guidance.
OPEN PDF 08EXTERIOR JOINT WRAPASTM C877 Type III and C923 external rubber joint wrap with cleaning, six-inch overlap and 360° application guidance.
OPEN PDF 09HEAT-SHRINK JOINT SEALPrimer and heat-shrink sleeve system for sealing manhole chimney and barrel joints in new construction or rehabilitation.
OPEN PDF05 / FIELD MODIFICATIONS
Polymer concrete can be cut, cored, drilled, and ground with the same equipment and diamond masonry tools used for standard concrete. We recommend contacting P3 before any field modification so we can review the location and share practical guidance for a clean result.